113710MARKET INTERVENTION24/01/2024 04:33:46 PM

Direction - SA region 24/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 24/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 24/01/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
113700MARKET INTERVENTION24/01/2024 02:41:12 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113695

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 25/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 24/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113695MARKET INTERVENTION24/01/2024 12:39:07 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 26/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113653MARKET INTERVENTION23/01/2024 03:54:22 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/01/2024

Refer Market Notice 113483

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs 23/01/2024

Manager NEM Real Time Operations
113649PRICES UNCHANGED22/01/2024 08:10:08 PM

[EventId:202401221945_confirmed] Prices for interval 22-Jan-2024 19:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 19:45.

In accordance with Market Notice 113639 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113648PRICES UNCHANGED22/01/2024 08:09:10 PM

[EventId:202401222005_confirmed] Prices for interval 22-Jan-2024 20:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 20:05.

In accordance with Market Notice 113643 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113647PRICES UNCHANGED22/01/2024 08:08:18 PM

[EventId:202401222000_confirmed] Prices for interval 22-Jan-2024 20:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 20:00.

In accordance with Market Notice 113642 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113646PRICES UNCHANGED22/01/2024 08:07:26 PM

[EventId:202401221955_confirmed] Prices for interval 22-Jan-2024 19:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 19:55.

In accordance with Market Notice 113641 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113645PRICES UNCHANGED22/01/2024 08:05:20 PM

[EventId:202401221950_confirmed] Prices for interval 22-Jan-2024 19:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 19:50.

In accordance with Market Notice 113640 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.