NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 16:30 to 21/05/2024 16:35
Amount: -19 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
Update Inter-Regional Transfer limit variation - Basslink 21/05/2024
Update Inter-Regional Transfer limit variation - Basslink
Refer AEMO Electricity Market Notice 116734
There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.
The following constraint set was revoked at 0810 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink 21/05/2024
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector at 0235 hrs
The following constraint set was invoked at 0240 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
[EventId:202405191545_review] Prices for interval 19-May-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191540_review] Prices for interval 19-May-2024 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191535_review] Prices for interval 19-May-2024 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191530_review] Prices for interval 19-May-2024 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191525_review] Prices for interval 19-May-2024 15:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs