CHG0089648 | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)
Change Start Date & Time: 16/05/2024 09:00:00 AEST
Change End Date & Time: 16/05/2024 12:00:00 AEST
Outage Start Date & Time: 16/05/2024 09:00:00 AEST
Outage End Date & Time: 16/05/2024 12:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region QLD1 Sunday, 19 May 2024
NON-CONFORMANCE QLD1 Region Sunday, 19 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: PUMP2
Duration: 19/05/2024 07:35 to 19/05/2024 07:40
Amount: 240 MW
Constraint: NC-Q_PUMP2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 18 May 2024
NON-CONFORMANCE QLD1 Region Saturday, 18 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/05/2024 02:40 to 18/05/2024 02:45
Amount: -14 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0089703 | Production | Planned System Maintenance activity.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.
Change Start Date & Time: 22/05/2024 11:00:00 AEST
Change End Date & Time: 22/05/2024 11:30:00 AEST
Outage Start Date & Time: 22/05/2024 11:00:00 AEST
Outage End Date & Time: 22/05/2024 11:30:00 AEST
Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region VIC1 Thursday, 16 May 2024
NON-CONFORMANCE VIC1 Region Thursday, 16 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NPS
Duration: 16/05/2024 15:20 to 16/05/2024 15:25
Amount: -15 MW
Constraint: NC-V_NPS
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024
Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.
Manager NEM Real Time Operations