Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115047 is cancelled at 1645 hrs 23/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1252 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024
Cancellation of Actual (LOR1) condition in the SA region - 21/02/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.114929 is cancelled at 1945 hrs 21/02/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Refer AEMO Electricity Market Notice 114927
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 428 MW
The minimum capacity reserve available is 277 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 21/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 431 MW
The minimum capacity reserve available is 414 MW
Manager NEM Real Time Operations
Update to system strength constraints in North Queensland
Refer to market notice 110677
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.
A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.
The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases.
Below constraint equations in the Q-NIL set will be modified:
- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I
AEMO Operations
Inter-regional transfer limit variation -Directlink DC2 - NSW region - 19/02/2024
Inter-regional transfer limit variation - Directlink DC2 - NSW region - 19/02/2024
A planned outage of Directlink DC2 in the NSW region was scheduled from 2000 hrs 16/02/2024 to 1701 hrs 20/02/2024.
The outage has been completed and Directlink DC2 returned to service at 1425 hrs 19/02/2024.
The following constraint set(s) revoked at 1425 hrs 19/02/2024
N-MBTE_1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Short Notice Outage - Directlink - NSW Region - 16 February 2024
Short Notice Outage - Directlink - NSW Region - 16 February 2024
A short notice outage of Directlink cable DC2 in the NSW Region.
Constraint set N-MBTE_1 invoked from 2010 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of all three legs of Directlink .
The following constraint set was invoked at 1440 hrs 16/02/2024
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations