86737RECLASSIFY CONTINGENCY07/06/2021 05:08:05 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 07/06/2021 17:08 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
86736PRICES SUBJECT TO REVIEW07/06/2021 05:05:19 PM

[EventId:202106071710_review] Prices for interval 07-Jun-2021 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 7 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 07-Jun-2021 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
86733MARKET INTERVENTION07/06/2021 05:59:08 PM

Direction - SA region 07/06/2021

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 07/06/2021

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1805 hrs on 07/06/2021.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
86731MARKET INTERVENTION07/06/2021 04:12:58 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units expected to be synchronised in SA from 1000 hrs 08/06/2021 to 1500 hrs 08/06/2021 in Pre-dispatch published at 1600 hrs 07/06/2021 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1800 hrs 07/06/2021, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
86730RECLASSIFY CONTINGENCY07/06/2021 03:02:06 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 1453 hrs 07/06/2021 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
86729RESERVE NOTICE07/06/2021 02:52:47 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/06/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 10/06/2021 to 1900 hrs 10/06/2021.
The forecast capacity reserve requirement is 1414 MW.
The minimum capacity reserve available is 1218 MW.

Operations Planning, AEMO
86728RESERVE NOTICE07/06/2021 02:49:57 PM

STPASA - Update Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 10/06/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 86701 has been updated at 1400 hrs 07/06/2021 to the following:

[1.] From 1730 hrs 10/06/2021 to 2030 hrs 10/06/2021.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 580 MW.

Operations Planning, AEMO
86727MARKET SYSTEMS07/06/2021 01:13:03 PM

CCHG0064858 - Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM) - CANCELLED

Due to Operational Reasons CHG0064858 has been Cancelled. A future scheduled date will be provided in due course.

Market Notice

Change Number: CHG0064858

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Expedited

Service/ Component: Declared Wholesale Gas Market

Change Title: Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)

Change Start Date & Time: 07/06/2021 18:00:00 AEST

Change End Date & Time: 07/06/2021 21:00:00 AEST

Outage Start Date & Time: 07/06/2021 18:30:00 AEST

Outage End Date & Time: 07/06/2021 20:30:00 AEST

Change Description:

Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)

Environment: Production

Participant Impact and Requirements:

DWGM market system (Webexchanger and MIBB) outage from 18:00 to 20:30 AEST on 07/06/21 due to unplanned maintenance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
86726MARKET SYSTEMS07/06/2021 12:25:58 PM

CHG0064858 - Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)

Market Notice

Change Number: CHG0064858

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Expedited

Service/ Component: Declared Wholesale Gas Market

Change Title: Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)

Change Start Date & Time: 07/06/2021 18:00:00 AEST

Change End Date & Time: 07/06/2021 21:00:00 AEST

Outage Start Date & Time: 07/06/2021 18:30:00 AEST

Outage End Date & Time: 07/06/2021 20:30:00 AEST

Change Description:

Unplanned System Maintenance - Declared Wholesale Gas Market (DWGM)

Environment: Production

Participant Impact and Requirements:

DWGM market system (Webexchanger and MIBB) outage from 18:00 to 20:30 AEST on 07/06/21 due to unplanned maintenance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm