[EventId:202106051840_review] Prices for interval 05-Jun-2021 18:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1835 hrs on 5 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 05-Jun-2021 18:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:139] AP STARTED for market ancillary services in QLD at 05 June 2021 17:30
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 5 June 2021
ADMINISTERED PRICE PERIOD DECLARED in QLD region.
AEMO has determined that the rolling sum of the uncapped market ancillary Raise 6 Sec services(s) prices for the QLD region over the previous 2016 dispatch intervals has exceeded 6 times the cumulative price threshold (CPT) of $224,600.00.
In accordance with Clause 3.14 of the National Electricity Rules, AEMO has determined that an administered price period will commence at the dispatch interval starting 1730 hrs on 5 Jun 2021 and will continue through to the end of that trading day.
An administered price cap (APC) of 300 $/MWh will apply to all dispatch intervals during this administered price period. This APC will apply to all market ancillary service prices in the QLD region.
An administered floor price (AFP) of 0 $/MWh AFP will apply to all market ancillary service prices.
AEMO will continue to monitor the rolling sum of the uncapped market ancillary service prices and issue further market notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:202106051700_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 05 June 2021 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 June 2021
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 5 June 2021.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1700 hrs on 5 June 2021.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 05/06/2021 15:39
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 86677
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region 05/06/2021
Direction - SA region 05/06/2021
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1705 hrs on 05/06/2021.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 05/06/2021 14:35 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in South Australia (SA) Region
Update - Possible intervention to manage power system security in South Australia (SA) Region
The combination of synchronous generating units currently expected to be synchronised in SA from 0030 hrs 06/06/2021 in Pre-dispatch will not provide sufficient system strength in SA to maintain the power system in a secure operating state.
In the absence of sufficient market response AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised from 0030 hrs 06/06/2021 to maintain power system security in SA. Refer to current Transfer Limit Advice for SA system strength on the AEMO website.
AEMO estimates the latest time at which AEMO would need to intervene is 1700 hrs on 05/06/2021.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 10/06/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1930 hrs 10/06/2021 to 2000 hrs 10/06/2021.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 869 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 04/06/2021
Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 04/06/2021
Refer Market Notice 86607
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs 05/06/20211
Manager NEM Real Time Operations