Market Notices

86756RECLASSIFY CONTINGENCY07/06/2021 10:57:45 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 07/06/2021 22:57

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 86741

Auto-generated on behalf of Manager NEM Real Time Operations
86755RECALL GEN CAPACITY07/06/2021 09:21:51 PM

Request for Generator Recall Information for the period for 10/06/2021 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 86754 [Intention to intervene MN]

Please provide Generator Recall Information for 10/06/2021 by 1700 hrs on 08/06/2021 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
86754RESERVE NOTICE07/06/2021 09:20:58 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 10/06/2021


AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1730 hrs 10/06/2021 to 1830 hrs 10/06/2021
The forecast capacity reserve requirement is 1278 MW.
The minimum capacity reserve available is 1116 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
86753GENERAL NOTICE07/06/2021 08:00:12 PM

Cancellation : Non-credible contingency event more likely to occur due to existence of abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.

Abnormal conditions advised in AEMO Electricity Market Notice 86715 have ceased to impact the likelihood of a non-credible event occurring as at 2000 hrs 07/06/2021

Manager NEM Real Time Operations
86752RESERVE NOTICE07/06/2021 08:17:04 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2021


AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:

[1.] From 1730 hrs 10/06/2021 to 2000 hrs 10/06/2021
The forecast capacity reserve requirement is 822 MW.
The minimum capacity reserve available is 553 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
86751PRICES UNCHANGED07/06/2021 05:40:18 PM

[EventId:202106071715_confirmed] Prices for interval 07-Jun-2021 17:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 7 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 17:15.

In accordance with Market Notice 86738 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86750PRICES UNCHANGED07/06/2021 05:39:13 PM

[EventId:202106071735_confirmed] Prices for interval 07-Jun-2021 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 7 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 17:35.

In accordance with Market Notice 86745 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86749PRICES UNCHANGED07/06/2021 05:37:35 PM

[EventId:202106071730_confirmed] Prices for interval 07-Jun-2021 17:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 7 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 17:30.

In accordance with Market Notice 86744 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86748PRICES UNCHANGED07/06/2021 05:38:27 PM

[EventId:202106071725_confirmed] Prices for interval 07-Jun-2021 17:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 7 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 07-Jun-2021 17:25.

In accordance with Market Notice 86743 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm