Market Notices

53528POWER SYSTEM EVENTS26/05/2016 04:39:17 PM

Update - Non-credible contingency event - SA region - 26/05/2016

AEMO ELECTRICITY MARKET NOTICE

Update - Non-credible contingency event - SA region - 26/05/2016

Update to Market Notice 53526

At 0851 hrs the South East - Tailem Bend No. 1 275 kV Line and the South East No. 1 275 kV SVC tripped.

At 0930 hrs the South East - Tailem Bend No. 1 275 kV Line was returned to service
At 1617 hrs the South East No. 1 275 kV SVC was returned to service

The following Constraint Sets were revoked at 1630 hrs.

S-SE_VC_1
V-2RP

See the AEMO Network Outage Scheduler (NOS) for further information

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
53527INTER-REGIONAL TRANSFER26/05/2016 09:41:40 AM

Update - Interregional Transfer Limit variation, South Australia Region Wednesday 26 May 2016

AEMO ELECTRICITY MARKET NOTICE

Interregional Transfer Limit Variation, South Australia Region Wednesday 26 May 2016

Update to Market Notice 53525

At 0930 hrs South East - Tailem Bend No.1 275 kV Line returned to service. The South East No.1 275 kV SVC remains out of service.

The following Constraint Set was revoked at 0945 hrs.

S-TBSE


See the AEMO Network Outage Scheduler (NOS) for further information

Manager NEM Real Time Operations
53526POWER SYSTEM EVENTS26/05/2016 09:14:35 AM

Non-credible contingency event - SA region - 26/05/2016

AEMO ELECTRICITY MARKET NOTICE

Non-credible contingency event - SA region - 26/05/2016

At 0851 hrs the South East Tailem Bend No. 1 275 kV Line and the South East No. 1 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
53525INTER-REGIONAL TRANSFER26/05/2016 09:20:23 AM

Interregional Transfer Limit variation, South Australia Region Wednesday 26 May 2016

AEMO ELECTRICITY MARKET NOTICE

Interregional Transfer Limit Variation, South Australia Region Wednesday 26 May 2016

At 0851 hrs, in the South Australia region the Tailem Bend to South East No.1 Line tripped in conjunction with the No.1 South East SVC.

Refer to Market Notice 53526

The following Constraint Sets have been invoked

S-TBSE at 0900 hrs
V-2RP at 0905 hrs
S-SE_VC_1 at 0905 hrs

These Constraint Sets contain equations with the following interconnector on the LHS

NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1
T-V-MNSP1

See the AEMO Network Outage Scheduler (NOS) for further information

Manager NEM Real Time Operations
53524NON-CONFORMANCE26/05/2016 08:30:14 AM

NON-CONFORMANCE Region QLD1 Thursday, 26 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 26 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: BRAEMAR3
Duration: 26/05/2016 08:20 to 26/05/2016 08:30
Amount: -36 MW
Constraint: NC-Q_BRAEMAR3

Auto-generated on behalf of Manager NEM Real Time Operations
53523MARKET SYSTEMS25/05/2016 07:18:16 PM

Planned System Maintenance (Site Transfer) on Market Settlement and Transfer Solutions (MSATS) Completed

Change Number: CHG0038481

Notification issued to: Market Notice


Notification Type: Completed

Change Type: Normal

Service/ Component: Market Settlements & Transfer System

Change Title: Planned System Maintenance (Site Transfer) on Market Settlement and Transfer Solutions (MSATS)

Change Description:
Transfer completed successfully

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
53522INTER-REGIONAL TRANSFER25/05/2016 05:03:29 PM

Inter-Regional Transfer Limit Variation - Lower Tumut to Yass (03) 330kV Transmission Line - NSW Region - 25 May 2016

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer Limit Variation - Lower Tumut to Yass (03) 330kV Transmission Line - NSW Region - 25 May 2016

The planned outage of Lower Tumut to Yass (03) 330kV Transmission Line was scheduled to complete at 1600 hrs 26/05/16.

The outage has completed early

The following constraint set for this outage was revoked at 1700 hrs 25/05/16
N-LTYS_03

The constraint set contains equations with the following interconnectors on the left hand side:
V-S-MNSP1
VIC1-NSW1

See AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
53521INTER-REGIONAL TRANSFER25/05/2016 04:25:00 PM

Interregional Transfer Limit variation, South Australia Region Wednesday 25 May 2016

AEMO ELECTRICITY MARKET NOTICE

Interregional Transfer Limit Variation, South Australia Region Wednesday 25 May 2016

At 1458hrs, the Canowie to Robertstown 275kV transmission line in the South Australia region tripped. .There was a prior planned outage of the Davenport to Canowie 275kV transmission line.

The following constraint sets are now invoked for these outages

S-X_DVCV+CNRB+RBCB
S-CNHL_HAL

The outage constraints contain equations with the following interconnector on the LHS

V-S-MNSP1

See the AEMO NOS for further information

Manager NEM Real Time Operations
53520MARKET SYSTEMS25/05/2016 02:22:23 PM

Planned System Change - EMMS Pre-Production: Generator Ramp Rate Rule Change

Change Number: CHG0039229

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System

Change Title: Planned System Change - EMMS Pre-Production: Generator Ramp Rate Rule Change

Change Start Date & Time: 30/05/2016 10:00:00 AEST

Change End Date & Time: 30/05/2016 12:00:00 AEST


Change Description:

This change is to support the new generator ramp rate rules starting on 1st July 2016.

As part of this change AEMO will publish data informing Participants of their Minimum Ramp Rates including Generator DUID and individual unit max capacities. (Refer to the AEMO Tech Spec 931 issued 18th March 2016 for more information.)

The new minimum Ramp Rates will become effective and be used in validation from trading day 08/06/16 in Pre-Production and from 01/07/16 in Production.

Environment: Pre-Production

Participant Impact and Requirements:

This rule change results in some DUIDs having a changed Minimum Ramp Rate used in offer validation. AEMO encourages participants to validate their own offering systems in Pre-Production before the Production implementation date.

AEMO reminds participants to ensure that any previously accepted offers are revised for compliance with the new Minimum Ramp Rate. AEMO will contact Participants if they are potentially in breach of the Minimum Ramp Rate rule requirements before the rule becomes effective.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm