Market Notices

53256RECLASSIFY CONTINGENCY15/05/2016 12:14:02 PM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

Refer AEMO Electricity Market Notice 53254

There is no longer any lightning activity has ceased in the vicinity of the the Farrell - Reece No. 1 and No. 2 220 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1215 hrs.

Constraint Sets F-T-FARE_N-2 revoked.


Manager NEM Real Time Operations
53255RECLASSIFY CONTINGENCY15/05/2016 12:13:47 PM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

Refer AEMO Electricity Market Notice 53253

There is no longer any lightning activity in the vicinity of the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1215 hrs.


Manager NEM Real Time Operations
53254RECLASSIFY CONTINGENCY15/05/2016 11:04:42 AM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

Lightning is occurring near the Farrell- Reece No. 1 and No. 2 220 kV Lines.

AEMO considers the simultaneous trip of those circuits to now be more likely.

Therefore AEMO has reclassified this as a credible contingency event from 1100
hrs 15 May 2015 until further notice.

Constraint Set F-T-FARE_N-2 invoked.


Manager NEM Real Time Operations
53253RECLASSIFY CONTINGENCY15/05/2016 10:35:26 AM

Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

Lightning is occurring near the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO considers the simultaneous trip of those circuits to now be more likely.

Therefore AEMO has reclassified this as a credible contingency event from 1030 hrs 15 May 2016 until further notice.

Manager NEM Real Time Operations
53245PRICES SUBJECT TO REVIEW15/05/2016 12:45:13 AM

[EventId:201605150050_review] Prices for interval 15-May-2016 00:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0045 hrs on 15 May 2016

PRICES ARE SUBJECT TO REVIEW for dispatch interval 15-May-2016 00:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
53244PRICES SUBJECT TO REVIEW15/05/2016 12:40:17 AM

[EventId:201605150045_review] Prices for interval 15-May-2016 00:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0040 hrs on 15 May 2016

PRICES ARE SUBJECT TO REVIEW for dispatch interval 15-May-2016 00:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
53242PRICES SUBJECT TO REVIEW15/05/2016 12:35:12 AM

[EventId:201605150040_review] Prices for interval 15-May-2016 00:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0035 hrs on 15 May 2016

PRICES ARE SUBJECT TO REVIEW for dispatch interval 15-May-2016 00:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
53240PRICES SUBJECT TO REVIEW15/05/2016 12:15:19 AM

[EventId:201605150020_review] Prices for interval 15-May-2016 00:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0015 hrs on 15 May 2016

PRICES ARE SUBJECT TO REVIEW for dispatch interval 15-May-2016 00:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
53238PRICES SUBJECT TO REVIEW15/05/2016 12:10:17 AM

[EventId:201605150015_review] Prices for interval 15-May-2016 00:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0010 hrs on 15 May 2016

PRICES ARE SUBJECT TO REVIEW for dispatch interval 15-May-2016 00:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2(b) of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.