Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Wednesday, 25 May 2016
NON-CONFORMANCE VIC1 Region Wednesday, 25 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 25/05/2016 00:00 to 25/05/2016 00:25
Amount: -27 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 23 May 2016
NON-CONFORMANCE NSW1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: SITHE01
Duration: 23/05/2016 06:35 to 23/05/2016 08:30
Amount: 23 MW
Constraint: NC-N_SITHE01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 23 May 2016
NON-CONFORMANCE SA1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: WATERLWF
Duration: 23/05/2016 03:35 to 23/05/2016 05:10
Amount: 107 MW
Constraint: NC-S_WATERLWF
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 23 May 2016
NON-CONFORMANCE VIC1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: HWPS3
Duration: 23/05/2016 04:20 to 23/05/2016 04:30
Amount: 11 MW
Constraint: NC-V_HWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 22 May 2016
NON-CONFORMANCE VIC1 Region Sunday, 22 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 22/05/2016 08:35 to 22/05/2016 08:40
Amount: 20 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 20 May 2016
NON-CONFORMANCE VIC1 Region Friday, 20 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS1
Duration: 20/05/2016 09:35 to 20/05/2016 10:05
Amount: 19 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 20 May 2016
NON-CONFORMANCE NSW1 Region Friday, 20 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: MP1
Duration: 20/05/2016 00:20 to 20/05/2016 00:25
Amount: -59 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:201605190100_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 19 May 2016 01:00
Issued by Australian Energy Market Operator Ltd at 0100 hrs on 19 May 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 19 May 2016.
Refer to market notice: 53406
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 0100 hrs on 19 May 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201605182340_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 18 May 2016 23:40
Issued by Australian Energy Market Operator Ltd at 2340 hrs on 18 May 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 18 May 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 2340 hrs on 18 May 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.