112154RESERVE NOTICE09/12/2023 06:50:27 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112137 is cancelled at 1850 hrs 09/12/2023.

Manager NEM Real Time Operations
112137RESERVE NOTICE09/12/2023 05:16:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.

Manager NEM Real Time Operations
112017RESERVE NOTICE05/12/2023 06:48:43 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112016 is cancelled at 1845 hrs 05/12/2023.

Manager NEM Real Time Operations
112016RESERVE NOTICE05/12/2023 06:21:33 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1350 MW

Manager NEM Real Time Operations
111947RESERVE NOTICE02/12/2023 07:47:01 PM

Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.111943 is cancelled at 1945 hrs 02/12/2023.

Manager NEM Real Time Operations
111943RESERVE NOTICE02/12/2023 06:20:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1820 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs

The capacity reserve requirement is 1299 MW
The minimum capacity reserve available is 1167 MW

Manager NEM Real Time Operations
111848POWER SYSTEM EVENTS29/11/2023 03:22:48 PM

Non-credible contingency event - QLD region - 29/11/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 29/11/2023

At 1421 hrs the R2 Braemar No.4 275 kV Busbar and R2 Braemar - S5 Western Downs No.8820 275 kV Line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
111796POWER SYSTEM EVENTS28/11/2023 01:52:36 PM

Update - Non-credible contingency event - SA region - 28/11/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 28/11/2023

Refer AEMO Electricity Market Notice 111779

Based on revised information, at 0534 hrs the Tungkillo- Robertstown No.1 and No.2 275kV lines tripped simultaneously. At 0536 hrs the Robertstown No.1 and No.2 synchronous condensers tripped simultaneously as a result.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
111779POWER SYSTEM EVENTS28/11/2023 05:53:09 AM

Non-credible contingency event - SA region - 28/11/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 28/11/2023

At 0536 hrs the Robertstown No1 syncon and the Robertstown No2 syncon tripped simultaneously.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations