Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations
CHG0069544 : 5MS - Market Trials Defect Release (Pre-Prod)
Change Number: CHG0069544
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: 5MS - Market Trials Defect Release (Pre-Prod)
Change Start Date & Time: 31/08/2021 18:00:00 AEST
Change End Date & Time: 01/09/2021 16:00:00 AEST
Outage Start Date & Time: 31/08/2021 18:00:00 AEST
Outage End Date & Time: 31/08/2021 20:00:00 AEST
Change Description:
This outage is to allow the deployment of MSATS and eEMDM Pre-Production as part of 5MS Market Trials . MSATS will be unavailable during this outage period.
Environment: Pre-Production
Participant Impact and Requirements:
There will be no access to the Pre-Production MSATS system for the duration of the outage. Please access outside these hours.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
INC0072513 : Marketnet VPN at Norwest having intermittent issues - Resolved
INC0072513 - Marketnet VPN at Norwest having intermittent issues - Resolved
Participants should now be able to connect to the Norwest site-site VPN
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
System Reconfiguration - QLD Region - 20/11/2020
System Reconfiguration - QLD Region - 20/11/2020
The following transmission equipment in the Queensland region has been returned to service at 275 kV - 20/11/2020
H13 Ross - H39 Woree No. 8966 275 kV Transmission line - previously operated as 132 kV feeders 7327, 7132 and 7301
The following transmission equipment in the Queensland region has been taken out of service - 20/11/2020
H32 Chalumbin - H39 Woree No. 877 275 kV Transmission line - due to risk of cable failure
The following transmission equipment in the Queensland region has been deenergised - 20/11/2020
H13 Ross - H32 Chalumbin No. 857 275 kV Transmission line - to free up a bay at H13 Ross for the 8966 275 kV line
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the Vic region - 25/01/2019
Cancellation of Actual (LOR3) condition in the Vic region - 25/01/2019
The Actual LOR3 Condition in the Vic region advised in AEMO Electricity Market Notice No.66768 is cancelled at 1350 hrs 25/01/219.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 25/01/2019
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 25/01/2019
Customer load shedding of non-interruptible load is occurring in the Vic region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the Vic region from 1100 hrs.
The Actual LOR3 condition is forecast to exist until 1500 hrs.
The load interrupted is 100 MW at 1100 hrs 25/01/2019. This may be varied during the actual LOR3 period.
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the Vic region - 24/01/2019
Cancellation of Actual (LOR3) condition in the Vic region - 24/01/2019
The Actual LOR3 Condition in the Vic region advised in AEMO Electricity Market Notice No.66670 is cancelled at 2000 hrs 24/01/2019.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 24/01/2019
Actual Lack Of Reserve Level 3 (LOR3) in the Vic region - 24/01/2019
Customer load shedding of non-interruptible load is occurring in the Vic region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the Vic region from 1810 hrs.
The Actual LOR3 condition is forecast to exist until 1910 hrs.
The maximum load to be interrupted is 266MW at 1810 hrs 24/01/2019