54209RESERVE NOTICE03/07/2016 02:32:56 PM

Update: Forecast Lack Of Reserve Level 1(LOR1) in the South Australia region - STPASA

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54201

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

1. From 06/07/2016 1830 hrs to 2100 hrs
The minimum reserve available is 285 MW.

2. From 07/07/2016 1830 hrs to 2030 hrs
The minimum reserve available is 289 MW.

3. From 08/07/2016 1830 hrs to 2000 hrs
The minimum reserve available is 316 MW.

The contingency capacity reserve required over the above periods of forecast LOR1 conditions is 400 MW.

Manager NEM Real Time Operations
54208GENERAL NOTICE03/07/2016 02:14:21 PM

Network Augmentation Commissioned - VIC Region, 3 July 2016

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned in the Victoria Region

Refer to Market Notice 51470.

The Ararat Terminal Station to Ararat Wind Farm 132kV transmission line was commissioned at 1250 hrs, 3 July 2016.

Manager NEM Real Time Operations
54201RESERVE NOTICE02/07/2016 02:27:19 PM

Update: Forecast Lack Of Reserve Level 1(LOR1) in the South Australia region - STPASA

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54188

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

1. From 04/07/2016 0830 hrs to 1000 hrs
The minimum reserve available is 308 MW.

2. From 06/07/2016 1830 hrs to 2000 hrs
The minimum reserve available is 345 MW.

3. From 07/07/2016 1830 hrs to 2000 hrs
The minimum reserve available is 326 MW.

4. From 08/07/2016 1900 hrs to 1930 hrs
The minimum reserve available is 368 MW.

The contingency capacity reserve required over the above periods of forecast LOR1 conditions is 400 MW.

Manager NEM Real Time Operations
54189GENERAL NOTICE01/07/2016 02:19:08 PM

Closure - Participant connectivity and network issues - 1 July 2016

AEMO ELECTRICITY MARKET NOTICE

Closure - Participant connectivity and network issues - 1 July 2016
Refer to MN 54186
Telstra have advised AEMO that the IPWAN issue is fully resolved.
For further details please contact the AEMO Information and Support Hub on 1300 236 600

Manager NEM Real Time Operations
54188RESERVE NOTICE01/07/2016 02:51:08 PM

Update: Forecast Lack Of Reserve Level 1(LOR1) in the South Australia region - STPASA - 4, 6 and 7 July 2016

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice(s) No. 54183.

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

1. From 04/07/2016 1800 hrs to 1900 hrs
The minimum reserve available is 365 MW.

2. From 06/07/2016 1800 hrs to 2100 hrs
The minimum reserve available is 273 MW.

3. From 07/07/2016 1800 hrs to 2100 hrs
The minimum reserve available is 217 MW.

The contingency capacity reserve required over the above periods of forecast LOR1 conditions is 400 MW.

Harmohan Singh
Operations Planning
54186GENERAL NOTICE30/06/2016 08:30:02 PM

Update - Participant connectivity and network issues - Thursday, 30 June 2016

AEMO ELECTRICITY MARKET NOTICE

Update - Participant connectivity and network issues - Thursday, 30 June 2016

Refer to MN 54185

Telstra have advised AEMO that the instability on the National IPWAN network has not yet been resolved.
This incident could affect market participant connectivity to AEMO via MarketNet.
An update will be provided as advised by Telstra.

For further details please contact the AEMO Information and Support Hub on 1300 236 600


Manager NEM Real Time Operations
54185GENERAL NOTICE30/06/2016 05:01:14 PM

Participant connectivity and network issues - Thursday, 30 June 2016

AEMO ELECTRICITY MARKET NOTICE

Participant connectivity and network issues - Thursday, 30 June 2016

Telstra have advised about instability on their National IPWAN network which could affect market participant connectivity to AEMO MarketNet. Currently AEMO has no reported impacts. An update will be provided as advised by Telstra.
For further details please contact the AEMO Information and Support Hub on 1300 236 600


Manager NEM Real Time Operations

54183RESERVE NOTICE30/06/2016 02:37:32 PM

Update: Forecast Lack Of Reserve Level 1(LOR1) in the South Australia region - STPASA - 6 July 2016

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54173 & 54178.

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period:

From 06/07/2016 1800 hrs to 2030 hrs
The contingency capacity reserve required is 400 MW.
The minimum reserve available is 296 MW.

Harmohan Singh
Operations Planning
54173RESERVE NOTICE29/06/2016 03:30:21 PM

Update: Forecast Lack Of Reserve Level 1(LOR1) in the South Australia region - STPASA - 4 to 6 July 2016

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54159 & 54172.

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

1. From 04/07/2016 1730 hrs to 2130 hrs
The minimum reserve available is 166 MW

2. From 05/07/2016 1830 hrs to 1930 hrs
The minimum reserve available is 378 MW

3. From 06/07/2016 1800 hrs to 2100 hrs
The minimum reserve available is 284 MW

The contingency capacity reserve required over the above periods of forecast LOR1 conditions is 400 MW.

Harmohan Singh
Operations Planning