STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:
[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.
[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127500
At 1050 hrs the Belmont - Loganlea 829 275 kV line was returned to service and previously (11/06/25) the Belmont (H3) No. 1 275 kV bus had returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127499
At 1713 hrs the Belmont (H3) No.1 275 kV bus and Loganlea - Belmont (829) 275 kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 11/06/2025
Non-credible contingency event - QLD region - 11/06/2025
At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/06/2025
Non-credible contingency event - VIC region - 06/06/2025
At 0830 hrs the Wodonga No 2 330kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 07/03/2025
Update - Non-credible contingency event - NSW region - 07/03/2025
Refer AEMO Electricity Market Notice 125536
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will no longer reclassify this event as a credible contingency event.
Region: NSW
Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line
Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025
Constraint set(s) invoked: NONE
Manager NEM Real Time Operations
Updated Victorian system normal voltage stability limit for the south-west Victoria
Refer to Market Notice 101368
AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.
The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.
Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
Update - Non-credible contingency event - NSW region - 19/04/2025
Update - Non-credible contingency event - NSW region - 19/04/2025
Refer AEMO Electricity Market Notice 126598
At 0617 hrs the Uralla - New England Solar Farm No.1 330/33 kV Transformer and New England No.2 Solar Farm was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 19/04/2025
Non-credible contingency event - NSW region - 19/04/2025
At 1351 hrs the Uralla - New England Solar Farm No.1 330/33 kV Transformer and New England No.2 Solar Farm tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations