Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127500
At 1050 hrs the Belmont - Loganlea 829 275 kV line was returned to service and previously (11/06/25) the Belmont (H3) No. 1 275 kV bus had returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127499
At 1713 hrs the Belmont (H3) No.1 275 kV bus and Loganlea - Belmont (829) 275 kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 11/06/2025
Non-credible contingency event - QLD region - 11/06/2025
At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 07/06/2025
A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:
Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:
Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line
Manager NEM Real Time Operations
[EventId:202506071630_review] Prices for interval 07-Jun-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071625_review] Prices for interval 07-Jun-2025 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071620_review] Prices for interval 07-Jun-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071615_review] Prices for interval 07-Jun-2025 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071610_review] Prices for interval 07-Jun-2025 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.