128168GENERAL NOTICE18/07/2025 02:05:37 PM

Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.

This outage is considered as a High Impact Outage (HIO).

During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
128164INTER-REGIONAL TRANSFER18/07/2025 12:18:28 PM

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

At 1207 hrs 18/07/2025 there was an unplanned outage of S3 Greenbank 275 kV SVC.

The following constraint set(s) invoked at 1215 hrs 18/07/2025
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
128151INTER-REGIONAL TRANSFER17/07/2025 03:15:24 PM

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.

The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025

Constraint set(s) revoked: Q-HACL

Manager NEM Real Time Operations
     
128143PRICES SUBJECT TO REVIEW16/07/2025 10:30:20 PM

[EventId:202507162235_review] Prices for interval 16-Jul-2025 22:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2230 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128142PRICES SUBJECT TO REVIEW16/07/2025 10:25:20 PM

[EventId:202507162230_review] Prices for interval 16-Jul-2025 22:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2225 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128141PRICES SUBJECT TO REVIEW16/07/2025 10:20:28 PM

[EventId:202507162225_review] Prices for interval 16-Jul-2025 22:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2220 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128140PRICES SUBJECT TO REVIEW16/07/2025 10:15:20 PM

[EventId:202507162220_review] Prices for interval 16-Jul-2025 22:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2215 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128139PRICES SUBJECT TO REVIEW16/07/2025 10:10:27 PM

[EventId:202507162215_review] Prices for interval 16-Jul-2025 22:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2210 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
128138PRICES SUBJECT TO REVIEW16/07/2025 10:05:27 PM

[EventId:202507162210_review] Prices for interval 16-Jul-2025 22:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2205 hrs on 16 July 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm