Market Notices

126346MARKET INTERVENTION05/04/2025 02:19:44 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126340

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0400 hrs 06/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 05/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126340MARKET INTERVENTION05/04/2025 12:53:42 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 06/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126339MARKET INTERVENTION05/04/2025 08:37:07 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126338

PPCCGT PELICAN POINT at 0930 hrs 05/04/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1630 hrs 05/04/2025.

The direction update is issued at 0835 hrs 05/04/2025.

Manager NEM Real Time Operations
     
126338MARKET INTERVENTION05/04/2025 07:57:52 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126337

PPCCGT PELICAN POINT at 0900 hrs 05/04/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1630 hrs 05/04/2025.

The direction update is issued at 0755 hrs 05/04/2025.

Manager NEM Real Time Operations
     
126337MARKET INTERVENTION05/04/2025 07:19:45 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126289

PPCCGT PELICAN POINT at 0830 hrs 05/04/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1630 hrs 05/04/2025.

The direction update is issued at 0715 hrs 05/04/2025.

Manager NEM Real Time Operations
     
126314MARKET INTERVENTION05/04/2025 03:55:59 AM

Cancellation - AEMO Intervention Event - SA region 03/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 03/04/2025

Refer to Market Notice 126248

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 05/04/2025.


Manager NEM Real Time Operations
     
126313MARKET INTERVENTION05/04/2025 03:55:35 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 126250

Direction is cancelled from: 0400 hrs 05/04/2025

Manager NEM Real Time Operations
     
126312MARKET INTERVENTION05/04/2025 01:25:50 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126287

Direction is cancelled from: 0130 hrs 05/04/2025

Manager NEM Real Time Operations
     
126291MARKET SYSTEMS04/04/2025 03:33:34 PM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025


During the window,FPP calculations may be delayed at various points.


Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm