126691MARKET INTERVENTION23/04/2025 12:38:14 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0100 hrs 24/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126690NON-CONFORMANCE23/04/2025 10:00:21 AM

NON-CONFORMANCE Region NSW1 Wednesday, 23 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 23 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JEMALNG1
Duration: 23/04/2025 08:50 to 23/04/2025 10:00
Amount: 38 MW
Constraint: NC-N_JEMALNG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126684MARKET INTERVENTION22/04/2025 02:21:02 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126643

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1530 hrs 23/04/2025.

The direction update is issued at 1420 hrs 22/04/2025.

Manager NEM Real Time Operations
     
126683MARKET INTERVENTION22/04/2025 02:22:28 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126644

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1715 hrs 23/04/2025.

The direction update is issued at 1420 hrs 22/04/2025.

Manager NEM Real Time Operations
     
126644MARKET INTERVENTION21/04/2025 02:06:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126635

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/04/2025.

The direction update is issued at 1410 hrs 21/04/2025.

Manager NEM Real Time Operations
     
126643MARKET INTERVENTION21/04/2025 02:05:15 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126604

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 23/04/2025.

The direction update is issued at 1405 hrs 21/04/2025.

Manager NEM Real Time Operations
     
126637MARKET INTERVENTION20/04/2025 08:43:30 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 126632

Direction is cancelled from: 2045 hrs 20/04/2025

Manager NEM Real Time Operations
     
126635MARKET INTERVENTION20/04/2025 08:34:30 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126602

TORRB2 TORRENS ISLAN at 2030 hrs 20/04/2025 to Synchronise and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is expected to stay in place until 0400 hrs 22/04/2025.

The direction update is issued at 2004 hrs 20/04/2025.

Manager NEM Real Time Operations
     
126632MARKET INTERVENTION20/04/2025 08:16:06 PM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 126592


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 2004 hrs 20/04/2025
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 2015 hrs 20/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 2045 hrs 20/04/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     