Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127489 is cancelled at 1400 hrs 10/06/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE- QLD region - 10/06/2025
Inter-regional transfer limit variation - Middle Ridge - Greenbank (8848) 275 kV LINE - QLD region - 10/06/2025
At 1000 hrs 10/06/2025 there was a short notice outage of Middle Ridge - Greenbank (8848) 275 kV LINE.
The following constraint set(s) invoked at 1030 hrs 10/06/2025
Q-MRGB_8848_8849
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127479 is cancelled at 1400 hrs 09/06/2025
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
The Forecast LOR1 condition advised in AEMO Electricity Market Notice No. 127478 for the NSW region has been updated at 1400 hrs 09/06/2025 to the following:
From 1730 hrs to 1900 hrs 12/06/2025.
The forecast capacity reserve requirement is 1753 MW.
The minimum capacity reserve available is 1664 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127487 is cancelled at 1345 hrs 09/06/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0800 hrs 10/06/2025 to 0900 hrs 10/06/2025.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 840 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/06/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127454 has been updated to the following:
[1.] From 0700 hrs 10/06/2025 to 0930 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 885 MW.
[2.] From 1630 hrs 10/06/2025 to 1700 hrs 10/06/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1105 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127402 has been updated to the following:
[1.] From 1700 hrs 12/06/2025 to 2100 hrs 12/06/2025.
The forecast capacity reserve requirement is 1691 MW.
The minimum capacity reserve available is 1532 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 07/06/2025
Cancellation - AEMO Intervention Event - SA region 07/06/2025
Refer to Market Notice 127455
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 08/06/2025.