[EventId:202505291735_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 May 2025 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 29 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 May 2025.
Refer to market notice: 127331
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1735 hrs on 29 May 2025.
This is an AEMO autogenerated Market Notice.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event .
Based on advice received from the asset owner, AEMO no longer considers the trip of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning as a credible contingency when there is lightning activity in the vicinity.
Accordingly the reclassification as a credible contingency is cancelled .
Region: TAS1
Element: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Cancellation time: 29/05/2025 1600 hrs
Constraint set(s) revoked: NONE
Refer AEMO Electricity Market Notices 125566
Manager NEM Real Time Operations
[EventId:202505291600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 May 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 29 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 29 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202505281845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 May 2025 18:45
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 28 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 May 2025.
Refer to market notice: 127328
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 28 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505281830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 28 May 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 28 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1830 hrs on 28 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202505281800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 28 May 2025 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 28 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 May 2025.
Refer to market notice: 127323
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 28 May 2025.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025
NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 28/05/2025 17:55 to 28/05/2025 18:00
Amount: -20 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202505281635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 28 May 2025 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 28 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 28 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 28 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025
NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 28/05/2025 12:30 to 28/05/2025 15:15
Amount: 26 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations