127626GENERAL NOTICE17/06/2025 01:30:24 PM

Planned outage of Moorabool - Cressy No 1 500 kV line in the VIC region on 19/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Moorabool - Cressy No 1 500 kV line in the Victoria (VIC) region is planned to be out of service from 0600 hrs to 1700 hrs on 19/06/2025.

A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM.

During this planned outage:

* Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
* Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
127625MARKET SYSTEMS17/06/2025 10:38:08 AM

Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0103463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127624MARKET SYSTEMS17/06/2025 10:32:34 AM

Completed - CHG0103273 - Scheduled Maintenance on Brisbane Datacentre

Change Number: CHG0103273

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled Maintenance on Brisbane Datacentre

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127596SETTLEMENTS RESIDUE16/06/2025 11:45:29 AM

[EventId:202506161145_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 11:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 16 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Refer to market notice: 127594

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1145 hrs on 16 June 2025.

This is an AEMO autogenerated Market Notice.
     
127594SETTLEMENTS RESIDUE16/06/2025 11:05:23 AM

[EventId:202506161105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 16 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 16 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127581SETTLEMENTS RESIDUE16/06/2025 10:30:20 AM

[EventId:202506161030_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 June 2025 10:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 16 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Refer to market notice: 127578

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1030 hrs on 16 June 2025.

This is an AEMO autogenerated Market Notice.
     
127578SETTLEMENTS RESIDUE16/06/2025 09:35:29 AM

[EventId:202506160935_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 June 2025 09:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 16 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0935 hrs on 16 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127573RESERVE NOTICE16/06/2025 07:15:27 AM

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 16/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127572 is cancelled at 0715 hrs 16/06/2025.

Manager NEM Real Time Operations
     
127572RESERVE NOTICE16/06/2025 06:44:29 AM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 16/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0630 hrs.
The Actual LOR1 condition is forecast to exist until 0730 hrs

The capacity reserve requirement is 700 MW
The minimum capacity reserve available is 638 MW

Manager NEM Real Time Operations
     