Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event .
Based on advice received from the asset owner, AEMO no longer considers the trip of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning as a credible contingency when there is lightning activity in the vicinity.
Accordingly the reclassification as a credible contingency is cancelled .
Region: TAS1
Element: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Cancellation time: 29/05/2025 1600 hrs
Constraint set(s) revoked: NONE
Refer AEMO Electricity Market Notices 125566
Manager NEM Real Time Operations
[EventId:202505271800_review] Prices for interval 27-May-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505271755_review] Prices for interval 27-May-2025 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505271750_review] Prices for interval 27-May-2025 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505271745_review] Prices for interval 27-May-2025 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505271740_review] Prices for interval 27-May-2025 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505271735_review] Prices for interval 27-May-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 27 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 27-May-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Refer to Market Notice 127159
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127276
Direction is cancelled from: 1400 hrs 27/05/2025
Manager NEM Real Time Operations