117677INTER-REGIONAL TRANSFER14/08/2024 04:22:12 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1620 hrs 14/08/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
117676NON-CONFORMANCE14/08/2024 03:20:18 PM

NON-CONFORMANCE Region SA1 Wednesday, 14 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 14 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 14/08/2024 10:30 to 14/08/2024 15:20
Amount: 26 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117672INTER-REGIONAL TRANSFER14/08/2024 11:08:17 AM

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

At 1006 hrs 14/08/2024 there was a short notice outage of CollectorWF-Marulan 4 330kV LINE.

The following constraint set(s) invoked at 1000 hrs 14/08/2024
N-CTMN_4_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117671RECLASSIFY CONTINGENCY14/08/2024 08:45:51 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 117660 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 0845hrs 14/08/2024.

No constraints were invoked during this event

Manager NEM Real Time Operations
     
117669INTER-REGIONAL TRANSFER14/08/2024 08:05:49 AM

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

A planned outage of Collector - Marulan No 4 330kV Line in the NSW region was scheduled from 0800 hrs 14/08/2024 to 1700 hrs 02/09/2024.


The outage has been cancelled.

Constraint set(s) invoked: N-CTMN_4_WG_CLOSE


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117667MARKET INTERVENTION13/08/2024 05:20:34 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117666

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0200 hrs 15/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 14/08/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
117666MARKET INTERVENTION13/08/2024 03:39:49 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0200 hrs 15/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
117665MARKET INTERVENTION13/08/2024 02:13:30 PM

Cancellation - AEMO Intervention Event - SA region 13/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 13/08/2024

Refer to Market Notice 117641

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 13/08/2024.



Manager NEM Real Time Operations
     
117664MARKET INTERVENTION13/08/2024 02:12:22 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117659

Direction is cancelled from: 1400 hrs 13/08/2024

Manager NEM Real Time Operations
     