117670GENERAL NOTICE14/08/2024 09:15:50 AM

Planned outage of Nebo to Broadsound no. 8846 275 kV line in the QLD region beginning on 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Nebo to Broadsound no. 8846 275 kV line in the Queensland (QLD) region is planned to be out of service from 0600 hrs 16/08/2024 to 1700 hrs 18/08/2024.

This outage is considered a High Impact Outage (HIO) as the outage recall is greater than 30 minutes.
A credible contingency event during this planned outage may require market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
117662SETTLEMENTS RESIDUE13/08/2024 11:20:27 AM

[EventId:202408131120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 August 2024 11:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1120 hrs on 13 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.

Refer to market notice: 117661

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 13 August 2024.

This is an AEMO autogenerated Market Notice.
     
117661SETTLEMENTS RESIDUE13/08/2024 10:35:30 AM

[EventId:202408131035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 August 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 13 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 13 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117650GENERAL NOTICE12/08/2024 09:31:53 AM

QNI Minor testing (NSW to Qld) 12th August 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 116052

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
117639NON-CONFORMANCE11/08/2024 03:41:15 PM

NON-CONFORMANCE Region SA1 Sunday, 11 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 11 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OSB-AG
Duration: 11/08/2024 15:30 to 11/08/2024 15:40
Amount: 52 MW
Constraint: NC-S_OSB-AG

Auto-generated on behalf of Manager NEM Real Time Operations
     
117631NON-CONFORMANCE11/08/2024 01:35:16 PM

NON-CONFORMANCE Region VIC1 Sunday, 11 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 11 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA4
Duration: 11/08/2024 13:05 to 11/08/2024 13:35
Amount: -61 MW
Constraint: NC-V_LYA4

Auto-generated on behalf of Manager NEM Real Time Operations
     
117624NON-CONFORMANCE10/08/2024 01:25:16 AM

NON-CONFORMANCE Region QLD1 Saturday, 10 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 10 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/08/2024 01:05 to 10/08/2024 01:25
Amount: -47 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117617PRICES SUBJECT TO REVIEW09/08/2024 07:55:10 PM

[EventId:202408092000_review] Prices for interval 09-Aug-2024 20:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1955 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 20:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117616PRICES SUBJECT TO REVIEW09/08/2024 07:50:19 PM

[EventId:202408091955_review] Prices for interval 09-Aug-2024 19:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1950 hrs on 9 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Aug-2024 19:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs