118193PRICES UNCHANGED08/09/2024 06:35:19 PM

[EventId:202409081820_confirmed] Prices for interval 08-Sep-2024 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:20.

In accordance with Market Notice 118187 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118183MARKET INTERVENTION08/09/2024 04:02:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118174

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 08/09/2024.

Manager NEM Real Time Operations
     
118182MARKET INTERVENTION08/09/2024 04:01:38 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118173

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 09/09/2024.

The direction update is issued at 1600 hrs 08/09/2024.

Manager NEM Real Time Operations
     
118174MARKET INTERVENTION07/09/2024 04:01:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118169

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 07/09/2024.

Manager NEM Real Time Operations
     
118173MARKET INTERVENTION07/09/2024 04:00:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118168

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 07/09/2024.

Manager NEM Real Time Operations
     
118171POWER SYSTEM EVENTS06/09/2024 08:18:58 PM

Update - Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 06/09/2024

Refer AEMO Electricity Market Notice 118166

At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
118169MARKET INTERVENTION06/09/2024 04:05:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118156

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.

The direction update is issued at 1600 hrs 06/09/2024.

Manager NEM Real Time Operations
     
118168MARKET INTERVENTION06/09/2024 04:04:10 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118155

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.

The direction update is issued at 1600 hrs 06/09/2024.

Manager NEM Real Time Operations
     
118166POWER SYSTEM EVENTS06/09/2024 12:38:00 PM

Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/09/2024

At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     