Market Notices

117756MARKET INTERVENTION22/08/2024 04:07:51 PM

Direction - SA region 22/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/08/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 22/08/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
117752MARKET INTERVENTION22/08/2024 02:42:40 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117751

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 23/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 22/08/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
117751MARKET INTERVENTION22/08/2024 01:16:19 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 23/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
117744NON-CONFORMANCE21/08/2024 10:00:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 21 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/08/2024 21:50 to 21/08/2024 22:00
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117743MARKET INTERVENTION21/08/2024 02:42:24 PM

Cancellation - AEMO Intervention Event - SA region 18/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 18/08/2024

Refer to Market Notice 117714

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 21/08/2024.



Manager NEM Real Time Operations
     
117742MARKET INTERVENTION21/08/2024 02:22:33 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117731

Direction is cancelled from: 1430 hrs 21/08/2024

Manager NEM Real Time Operations
     
117741MARKET INTERVENTION21/08/2024 12:30:52 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 117732

Direction is cancelled from: 1230 hrs 21/08/2024

Manager NEM Real Time Operations
     
117733MARKET INTERVENTION20/08/2024 04:24:49 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 117719

Direction is cancelled from: 1630 hrs 20/08/2024

Manager NEM Real Time Operations
     
117732MARKET INTERVENTION20/08/2024 04:13:48 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAND

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117722


TORRB4 TORRENS ISLAND to synchronise at 0900 hrs 21/08/2024

This update is issued at 1600 hrs 20/08/2024 and is expected to stay in place until 1230 hrs 21/08/2024