128036MARKET INTERVENTION09/07/2025 11:16:25 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 128015

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 09/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 09/07/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
128035MARKET INTERVENTION09/07/2025 07:30:34 AM

Cancellation - AEMO Intervention Event - SA region 08/07/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 08/07/2025

Refer to Market Notice 128006

The AEMO Intervention Event and all associated directions are cancelled from 0730 hrs on 09/07/2025.


Manager NEM Real Time Operations
     
128034MARKET INTERVENTION09/07/2025 07:30:24 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 128012

Direction is cancelled from: 0730 hrs 09/07/2025

Manager NEM Real Time Operations
     
128033RESERVE NOTICE09/07/2025 12:23:25 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128031 is cancelled at 0025 hrs 09/07/2025.

Manager NEM Real Time Operations
     
128031RESERVE NOTICE08/07/2025 07:49:17 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1000 hrs 11/07/2025 to 1030 hrs 11/07/2025.
The forecast capacity reserve requirement is 833 MW.
The minimum capacity reserve available is 819 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
128030RECLASSIFY CONTINGENCY08/07/2025 06:58:44 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127999 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1905 hrs 08/07/2025

Constraint set(s) revoked: I-VS_250



Manager NEM Real Time Operations
     
128015MARKET INTERVENTION08/07/2025 05:22:32 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 09/07/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
128012MARKET INTERVENTION08/07/2025 02:45:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 128007

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0730 hrs 09/07/2025.

The direction update is issued at 1445 hrs 08/07/2025.

Manager NEM Real Time Operations
     
128011MARKET SYSTEMS08/07/2025 12:33:46 PM

Electricity Market Management System_PreProd

Change Number: CHG0104481

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Update Shareplex NuTCracker resource allocation

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm