Market Notices

127863RECLASSIFY CONTINGENCY25/06/2025 04:34:25 PM

Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Cancellation time: 25/06/2025 16:34

Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127855

Auto-generated on behalf of Manager NEM Real Time Operations
     
127855RECLASSIFY CONTINGENCY25/06/2025 03:29:35 PM

Reclassification of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Duration: 25/06/2025 15:29 until further notice

Constraint set(s) invoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
127844MARKET INTERVENTION25/06/2025 02:02:08 PM

Cancellation - AEMO Intervention Event - SA region 21/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 21/06/2025

Refer to Market Notice 127682

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.


Manager NEM Real Time Operations
     
127843MARKET INTERVENTION25/06/2025 02:01:53 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127792

Direction is cancelled from: 1400 hrs 25/06/2025

Manager NEM Real Time Operations
     
127838RECLASSIFY CONTINGENCY25/06/2025 10:01:33 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127815 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1000 hrs 25/06/2025

Constraint set(s) revoked: I-VS_250



Manager NEM Real Time Operations
     
127837RECLASSIFY CONTINGENCY25/06/2025 10:01:23 AM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 1000 hrs 25/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127749

Manager NEM Real Time Operations
     
127836RECLASSIFY CONTINGENCY25/06/2025 10:01:23 AM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 1000 hrs 25/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127748

Manager NEM Real Time Operations
     
127832RECLASSIFY CONTINGENCY24/06/2025 09:59:26 PM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 24/06/2025 21:59

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-GH_RC12_250 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127826

Auto-generated on behalf of Manager NEM Real Time Operations
     
127831RECLASSIFY CONTINGENCY24/06/2025 09:59:26 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 24/06/2025 21:59

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127825

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm