127877MARKET SYSTEMS27/06/2025 09:08:43 AM

CHG0103089 - ERI & STPASA Recall Period Production Release

Change Number: CHG0103089

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025

Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127876RESERVE NOTICE27/06/2025 08:44:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0730 hrs to 0800 hrs 30/06/2025.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 828 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
127869RESERVE NOTICE26/06/2025 10:38:06 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127862 is cancelled at 1000 hrs 26/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127868RESERVE NOTICE26/06/2025 10:37:41 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127861 is cancelled at 1000 hrs 26/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127862RESERVE NOTICE25/06/2025 04:35:54 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127850 has been updated at 1500 hrs 25/06/2025 to the following:

From 0000 hrs to 0330 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 169 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127861RESERVE NOTICE25/06/2025 04:35:54 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127849 has been updated at 1500 hrs 25/06/2025 to the following:

1. From 0400 hrs to 1130 hrs 02/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 99 MW.

2. From 1630 hrs to 2359 hrs 02/07/2025.
The forecast capacity reserve requirement is 240 MW.
The minimum capacity reserve available is 77 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127850RESERVE NOTICE25/06/2025 02:48:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127849RESERVE NOTICE25/06/2025 02:48:33 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0400 hrs to 0630 hrs 02/07/2025.
The forecast capacity reserve requirement is 242 MW.
The minimum capacity reserve available is 0 MW.

2. From 1100 hrs to 1230 hrs 02/07/2025.
The forecast capacity reserve requirement is 231 MW.
The minimum capacity reserve available is 7 MW.

3. From 1600 hrs to 1700 hrs 02/07/2025.
The forecast capacity reserve requirement is 248 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127844MARKET INTERVENTION25/06/2025 02:02:08 PM

Cancellation - AEMO Intervention Event - SA region 21/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 21/06/2025

Refer to Market Notice 127682

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.


Manager NEM Real Time Operations
     