117935MARKET INTERVENTION28/08/2024 05:15:23 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117929

The TORRB3 TORRENS ISLAN direction is now expected to synhronise at 1330 hrs 29/08/2024.

The direction update is issued at 1710 hrs 28/08/2024.

Manager NEM Real Time Operations
     
117929MARKET INTERVENTION28/08/2024 03:50:27 PM

Direction - SA region 26/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 26/08/2024

Refer to Market Notice 117813


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 28/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1200 hrs 29/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 30/08/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
117928MARKET INTERVENTION28/08/2024 03:48:25 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117892

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 30/08/2024.

The direction update is issued at 1548 hrs 28/08/2024.

Manager NEM Real Time Operations
     
117919MARKET INTERVENTION28/08/2024 10:02:52 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117894

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 28/08/2024.

The direction update is issued at 1000 hrs 28/08/2024.

Manager NEM Real Time Operations
     
117909POWER SYSTEM EVENTS28/08/2024 02:17:12 AM

Update - Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 28/08/2024

Refer AEMO Electricity Market Notice 117908

At 0134 hrs the APD No 2 Potline was returned to service.

At 0200 hrs the APD No 1 Potline was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
117908POWER SYSTEM EVENTS28/08/2024 01:02:22 AM

Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 28/08/2024

At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.

AEMO did not instruct load shedding.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117903PRICES UNCHANGED27/08/2024 04:09:19 PM

[EventId:202408271545_confirmed] Prices for interval 27-Aug-2024 15:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 15:45.

In accordance with Market Notice 117891 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117902PRICES UNCHANGED27/08/2024 04:11:54 PM

[EventId:202408271605_confirmed] Prices for interval 27-Aug-2024 16:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 16:05.

In accordance with Market Notice 117897 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117901PRICES UNCHANGED27/08/2024 04:08:12 PM

[EventId:202408271600_confirmed] Prices for interval 27-Aug-2024 16:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 16:00.

In accordance with Market Notice 117896 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     