NON-CONFORMANCE Region QLD1 Saturday, 10 August 2024
NON-CONFORMANCE QLD1 Region Saturday, 10 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/08/2024 01:05 to 10/08/2024 01:25
Amount: -47 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0091753 | Completed | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095132 | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Change Start Date & Time: 13/08/2024 22:30:42 AEST
Change End Date & Time: 14/08/2024 08:30:42 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0095134 | Production | AEMO will be undertaking maintenance activities on the SMP system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the SMP system
Change Start Date & Time: 11/08/2024 15:00:57 AEST
Change End Date & Time: 12/08/2024 01:00:57 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the SMP system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation - AEMO Intervention Event - SA region 07/08/2024
Cancellation - AEMO Intervention Event - SA region 07/08/2024
Refer to Market Notice 117577
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/08/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 117578
Direction is cancelled from: 1500 hrs 08/08/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 117576
Direction is cancelled from: 1500 hrs 08/08/2024
Manager NEM Real Time Operations
Network Augmentation Commissioned - VIC Region - 07/08/2024
Network Augmentation Commissioned - VIC Region - 07/08/2024
Cressy - Golden Plains No. 2 220 kV Line has been commissioned.
Manager NEM Real Time Operations
Direction - SA region 07/08/2024
Direction - SA region 07/08/2024
Refer to Market Notice 117573
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1500 hrs 07/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 2230 hrs 07/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 08/08/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations