NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025
NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region beginning on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs 02/07/2025 to 0400 hrs 02/07/2025.
The forecast capacity reserve requirement is 239 MW.
The minimum capacity reserve available is 193 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127812 has been updated at 1830 hrs 24/06/2025 to the following:
[1.] From 0400 hrs 01/07/2025 to 1000 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 123 MW.
2. From 1700 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 234 MW.
The minimum capacity reserve available is 97 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127811 has been updated at 1600 hrs 24/06/2025 to the following:
1. From 0400 hrs to 1100 hrs 01/07/2025.
The forecast capacity reserve requirement is 226 MW.
The minimum capacity reserve available is 0 MW.
2. From 1630 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 237 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127781 has been updated at 1500 hrs 24/06/2025 to the following:
1. From 0400 hrs to 1100 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 106 MW.
2. From 1630 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 237 MW.
The minimum capacity reserve available is 84 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 30/06/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127776 is cancelled at 1500 hrs 24/06/2025.
AEMO Operations
[EventId:202506241515_review] Prices for interval 24-Jun-2025 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241510_review] Prices for interval 24-Jun-2025 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506241505_review] Prices for interval 24-Jun-2025 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jun-2025 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.