127792MARKET INTERVENTION24/06/2025 03:51:40 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127740

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.

The direction update is issued at 1600 hrs 24/06/2025.

Manager NEM Real Time Operations
     
127773RESERVE NOTICE24/06/2025 09:45:42 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127753 is cancelled at 0900 hrs on 24/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127753RESERVE NOTICE23/06/2025 09:53:46 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:

[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.

[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127747MARKET INTERVENTION23/06/2025 07:09:33 PM

Cancellation - Direction - NSW region - 23/06/2025

AEMO ELECTRICITY PARTICIPANT NOTICE

Cancellation - Direction - NSW region - 23/06/2025

Refer to Market Notice 127745.

The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.

Manager NEM Real Time Operations
     
127745MARKET INTERVENTION23/06/2025 06:00:38 PM

Direction - NSW region 23/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Direction - NSW region 23/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.

A further market notice will be issued when all directions related to this requirement have been cancelled.

For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).


Manager NEM Real Time Operations
     
127743INTER-REGIONAL TRANSFER23/06/2025 05:44:44 PM

Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025

At 1719 hrs 23/06/2025 there was an unplanned outage of Darlington Point - Wagga No.63 330 kV line. The Darlington Point - Balranald No. X5 220 kV line consequently tripped due to a control scheme for the trip of the above line as per design.

The following constraint set(s) invoked at 1725 hrs 23/06/2025
N-DPWG_63_X5

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127740MARKET INTERVENTION23/06/2025 02:59:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127696

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/06/2025.

The direction update is issued at 1500 hrs 23/06/2025.

Manager NEM Real Time Operations
     
127696MARKET INTERVENTION22/06/2025 03:01:04 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127683

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/06/2025.

The direction update is issued at 1500 hrs 22/06/2025.

Manager NEM Real Time Operations
     
127683MARKET INTERVENTION21/06/2025 04:04:12 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127679


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 21/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 21/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 23/06/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm