117487POWER SYSTEM EVENTS27/07/2024 10:52:18 AM

Correction - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Correction to Market Notice 117486

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
117486POWER SYSTEM EVENTS27/07/2024 10:26:53 AM

Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
117477MARKET SYSTEMS26/07/2024 05:11:06 PM

CHG0091533 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0091533
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 08/08/2024 22:00:00 AEST
Outage Start Date & Time: 08/08/2024 18:30:00 AEST
Outage End Date & Time: 08/08/2024 21:00:00 AEST
Environment: Production

Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
117440SETTLEMENTS RESIDUE25/07/2024 11:15:22 AM

[EventId:202407251115_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 July 2024 11:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1115 hrs on 25 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.

Refer to market notice: 117439

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1115 hrs on 25 July 2024.

This is an AEMO autogenerated Market Notice.
     
117439SETTLEMENTS RESIDUE25/07/2024 10:00:21 AM

[EventId:202407251000_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 July 2024 10:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 25 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1000 hrs on 25 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117412MARKET SYSTEMS22/07/2024 09:52:44 AM

CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.

Change Number: CHG0090458
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117403MARKET SYSTEMS21/07/2024 02:12:21 PM

CHG0091275 | Completed | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade

Change Number: CHG0091275
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117388SETTLEMENTS RESIDUE20/07/2024 02:30:21 PM

[EventId:202407201430_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 20 July 2024 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 20 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Refer to market notice: 117382

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1430 hrs on 20 July 2024.

This is an AEMO autogenerated Market Notice.
     
117382SETTLEMENTS RESIDUE20/07/2024 01:30:31 PM

[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.