127852NON-CONFORMANCE25/06/2025 02:45:13 PM

NON-CONFORMANCE Region VIC1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LVES1
Duration: 25/06/2025 14:25 to 25/06/2025 14:45
Amount: 63 MW
Constraint: NC-V_LVES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127851NON-CONFORMANCE25/06/2025 02:40:13 PM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 25/06/2025 14:25 to 25/06/2025 14:40
Amount: 6 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127850RESERVE NOTICE25/06/2025 02:48:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127849RESERVE NOTICE25/06/2025 02:48:33 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0400 hrs to 0630 hrs 02/07/2025.
The forecast capacity reserve requirement is 242 MW.
The minimum capacity reserve available is 0 MW.

2. From 1100 hrs to 1230 hrs 02/07/2025.
The forecast capacity reserve requirement is 231 MW.
The minimum capacity reserve available is 7 MW.

3. From 1600 hrs to 1700 hrs 02/07/2025.
The forecast capacity reserve requirement is 248 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127840RESERVE NOTICE25/06/2025 12:02:06 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127819 and Market Notice No. 127782 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127839RESERVE NOTICE25/06/2025 12:01:51 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127818 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127833NON-CONFORMANCE25/06/2025 06:10:17 AM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127819RESERVE NOTICE24/06/2025 06:42:59 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region beginning on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs 02/07/2025 to 0400 hrs 02/07/2025.
The forecast capacity reserve requirement is 239 MW.
The minimum capacity reserve available is 193 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127818RESERVE NOTICE24/06/2025 06:42:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127812 has been updated at 1830 hrs 24/06/2025 to the following:

[1.] From 0400 hrs 01/07/2025 to 1000 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 123 MW.

2. From 1700 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 234 MW.
The minimum capacity reserve available is 97 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm