Market Notices

127833NON-CONFORMANCE25/06/2025 06:10:17 AM

NON-CONFORMANCE Region QLD1 Wednesday, 25 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 25 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BARRON-2
Duration: 25/06/2025 06:05 to 25/06/2025 06:10
Amount: -25 MW
Constraint: NC-Q_BARRON-2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127793RESERVE NOTICE24/06/2025 03:11:48 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127741 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 1100 hrs to 1130 hrs 01/07/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 377 MW.

2. From 1600 hrs to 1630 hrs 01/07/2025.
The forecast capacity reserve requirement is 410 MW.
The minimum capacity reserve available is 301 MW.

AEMO Operations
     
127792MARKET INTERVENTION24/06/2025 03:51:40 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127740

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.

The direction update is issued at 1600 hrs 24/06/2025.

Manager NEM Real Time Operations
     
127789RESERVE NOTICE24/06/2025 03:11:38 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127739 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 0600 hrs to 0700 hrs 30/06/2025.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 473 MW.

2. From 1030 hrs to 1100 hrs 30/06/2025.
The forecast capacity reserve requirement is 376 MW.
The minimum capacity reserve available is 268 MW.

3. From 1630 hrs to 1700 hrs 30/06/2025.
The forecast capacity reserve requirement is 397 MW.
The minimum capacity reserve available is 200 MW.

AEMO Operations
     
127787RESERVE NOTICE24/06/2025 03:11:28 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0630 hrs to 0830 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1123 MW.

2. From 1630 hrs to 2300 hrs 30/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1073 MW.

AEMO Operations
     
127785RESERVE NOTICE24/06/2025 03:11:17 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127738 has been updated at 1400 hrs 24/06/2025 to the following:

1. From 0600 hrs to 0800 hrs 26/06/2025.
The forecast capacity reserve requirement is 1748 MW.
The minimum capacity reserve available is 1714 MW.

2. From 1630 hrs to 2300 hrs 26/06/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1636 MW.

AEMO Operations
     
127780NON-CONFORMANCE24/06/2025 01:30:16 PM

NON-CONFORMANCE Region VIC1 Tuesday, 24 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 24 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 24/06/2025 13:00 to 24/06/2025 13:30
Amount: 15 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127747MARKET INTERVENTION23/06/2025 07:09:33 PM

Cancellation - Direction - NSW region - 23/06/2025

AEMO ELECTRICITY PARTICIPANT NOTICE

Cancellation - Direction - NSW region - 23/06/2025

Refer to Market Notice 127745.

The requirement for AEMO to issue a direction to maintain the power system in a secure operating state has ended. All associated directions are cancelled from 1907hrs on 23/06/2025.

Manager NEM Real Time Operations
     
127745MARKET INTERVENTION23/06/2025 06:00:38 PM

Direction - NSW region 23/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Direction - NSW region 23/06/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the NSW region.

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.

A further market notice will be issued when all directions related to this requirement have been cancelled.

For the purposes of the National Electricity Rules this was a clause 4.8.9 instruction under clause 4.8.9(a).


Manager NEM Real Time Operations
     