Non-credible contingency event - VIC region - 06/06/2025
Non-credible contingency event - VIC region - 06/06/2025
At 0830 hrs the Wodonga No 2 330kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Completed - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Initial - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 05/06/2025 08:00:00
Change End Date & Time: 06/06/2025 17:00:00
Outage Start Date & Time: 05/06/2025 08:00:00
Outage End Date & Time: 05/06/2025 21:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Initial - CHG0103461 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 05/06/2025 08:00:00
Change End Date & Time: 06/06/2025 17:00:00
Outage Start Date & Time: 05/06/2025 08:00:00
Outage End Date & Time: 05/06/2025 21:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
CHG0103386 | Production | Renewal and update of AEMO's FBS-Prod-Hub.aemo.com.au server certificate
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to "FBS-Prod-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Prod-Hub.aemo.com.au
apis.prod.aemo.com.au
hub.aemo.com.au
prod.frchub.net
apis.prod.marketnet.net.au
hub.marketnet.net.au
Participants WILL need to update the profile that communicates with the above domains. This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below: https://www.digicert.com/secure/download-certificate/0zb6n7hdvs5c84j41twxz695ft63p2m
Change duration will be as below.
Start - 22/06/2025 10:00:00 AM AEST
End - 22/06/2025 14:00:00 PM AEST
CHG0103461 | EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities.
Change Start Date & Time 05/06/2025 08:00:00 AEST
Change End Date & Time 06/06/2025 17:00:00 AEST
Outage Start Date & Time 05/06/2025 08:00:00 AEST
Outage End Date & Time 05/06/2025 21:00:00 AEST
EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on 5th June.
During the window,FPP calculations may be delayed at various points.
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Resolved - INC0145274 - Markets Portal - Unable to View Menu
SERVICE INTERRUPTION - RESOLVED
The service interruption relating to the Market Portal has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
Completed - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update - Non-credible contingency event - NSW region - 07/03/2025
Update - Non-credible contingency event - NSW region - 07/03/2025
Refer AEMO Electricity Market Notice 125536
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will no longer reclassify this event as a credible contingency event.
Region: NSW
Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line
Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025
Constraint set(s) invoked: NONE
Manager NEM Real Time Operations