Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW
Manager NEM Real Time Operations
[EventId:202504101700_confirmed] Prices for interval 10-Apr-2025 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:00.
In accordance with Market Notice 126474 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101725_confirmed] Prices for interval 10-Apr-2025 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:25.
In accordance with Market Notice 126480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101720_confirmed] Prices for interval 10-Apr-2025 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:20.
In accordance with Market Notice 126479 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101715_confirmed] Prices for interval 10-Apr-2025 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:15.
In accordance with Market Notice 126478 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101710_confirmed] Prices for interval 10-Apr-2025 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:10.
In accordance with Market Notice 126476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_confirmed] Prices for interval 10-Apr-2025 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:05.
In accordance with Market Notice 126475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025
NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1
Auto-generated on behalf of Manager NEM Real Time Operations
Release of PEC-1 and combined V-SA limits - 11 April 2025
Refer to market notice 123956
AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.
The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.
With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.