Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 11/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Release of PEC-1 and combined V-SA limits - 11 April 2025
Refer to market notice 123956
AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.
The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.
With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 10/04/2025
Refer Market Notice 126440
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1430 hrs 09/04/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 10/04/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Completed - CHG0102439 - NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inital - CHG0102487 - Frequency Performance Payments (FPP) Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments (FPP) Maintenance Release
Change Start Date & Time: 10/04/2025 08:00:00
Change End Date & Time: 10/04/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of FPP calculation results may be delayed at times during the maintenance window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Inital - CHG0100085 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 14/04/2025 08:00:00
Change End Date & Time: 16/04/2025 19:00:00
Outage Start Date & Time: 15/04/2025 13:15:00
Outage End Date & Time: 15/04/2025 14:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inital - CHG0100211 - Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Change Start Date & Time: 15/04/2025 10:00:00
Change End Date & Time: 15/04/2025 18:00:00
Outage Start Date & Time: 15/04/2025 13:05:00
Outage End Date & Time: 15/04/2025 13:15:00
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Internal / Markets Portal Services
Identity Service may cause users to experience few session issues for few logins initated between 13:05 to 13:15 Market Time.
Internal / Market Portal Services will have an outage due to EMMS site transfer activities carried out along with this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Cancellation - Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
The foreseeable circumstance identified in Market Notice 126418 is cancelled.
Manager NEM Real Time Operations