Market Notices

127856SETTLEMENTS RESIDUE25/06/2025 03:35:15 PM

[EventId:202506251535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 25 June 2025 15:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 25 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1535 hrs on 25 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127850RESERVE NOTICE25/06/2025 02:48:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127849RESERVE NOTICE25/06/2025 02:48:33 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0400 hrs to 0630 hrs 02/07/2025.
The forecast capacity reserve requirement is 242 MW.
The minimum capacity reserve available is 0 MW.

2. From 1100 hrs to 1230 hrs 02/07/2025.
The forecast capacity reserve requirement is 231 MW.
The minimum capacity reserve available is 7 MW.

3. From 1600 hrs to 1700 hrs 02/07/2025.
The forecast capacity reserve requirement is 248 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127840RESERVE NOTICE25/06/2025 12:02:06 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127819 and Market Notice No. 127782 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127839RESERVE NOTICE25/06/2025 12:01:51 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127818 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127834GENERAL NOTICE25/06/2025 08:54:58 AM

Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.

A credible contingency event during this planned outage may require:

* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
127829SETTLEMENTS RESIDUE24/06/2025 09:30:24 PM

[EventId:202506242130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 21:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2130 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127824

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2130 hrs on 24 June 2025.

This is an AEMO autogenerated Market Notice.
     
127824SETTLEMENTS RESIDUE24/06/2025 08:35:21 PM

[EventId:202506242035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 June 2025 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 24 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2035 hrs on 24 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127823SETTLEMENTS RESIDUE24/06/2025 08:00:35 PM

[EventId:202506242000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127821

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2000 hrs on 24 June 2025.

This is an AEMO autogenerated Market Notice.
     