Market Notices

127484MARKET SYSTEMS09/06/2025 01:25:11 AM

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

INC0145687 - RESOLVED - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - RESOLVED

The service interruption relating to Frequency Performance Payments (FPP) System has been resolved.

The FPP System started normal operations from 00:25 Hrs AEST on 09/06/2025

Default Contribution Factors (DCFs) will be used for Regulation Frequency Control Ancillary Service (FCAS) recovery for the trading intervals where CFs were not calculated. No FPP amount will be paid or due for those Trading Intervals.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
127483MARKET SYSTEMS09/06/2025 12:02:59 AM

INC0145687 - ALERT - Frequency Performance Payments (FPP) Syste

INC0145687 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to Frequency Performance Payments (FPP) System.

The service interruption started from 20:25 hrs AEST on 08/06/2025. The participants will experience a delay in receiving FPP factors.

AEMO is working on resolving the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au


































     
127473RECLASSIFY CONTINGENCY07/06/2025 11:47:43 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127419

Manager NEM Real Time Operations
     
127472RECLASSIFY CONTINGENCY07/06/2025 11:47:22 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127418

Manager NEM Real Time Operations
     
127471RECLASSIFY CONTINGENCY07/06/2025 11:47:12 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127450 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 2345 hrs 7/06/2025

Constraint set(s) revoked:
I-VS_250

Manager NEM Real Time Operations
     
127450RECLASSIFY CONTINGENCY07/06/2025 12:51:59 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action to maintain power system security at 1250 hrs 07/06/2025.
Constraint set invoked:
I-VS_250
Duration: 1255 hrs until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
     
127444RECLASSIFY CONTINGENCY07/06/2025 09:44:30 AM

Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Cancellation time: 07/06/2025 09:44

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127434

Auto-generated on behalf of Manager NEM Real Time Operations
     
127443RECLASSIFY CONTINGENCY07/06/2025 09:34:32 AM

Cancellation of a Non-Credible Contingency Event: Sheffield - George Town 1 & 2 220kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Sheffield - George Town 1 & 2 220kV and

Cancellation time: 07/06/2025 09:34

Constraint set(s) revoked:
T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 127437

Auto-generated on behalf of Manager NEM Real Time Operations
     
127441RECLASSIFY CONTINGENCY07/06/2025 09:14:32 AM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 07/06/2025 09:14

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 127436

Auto-generated on behalf of Manager NEM Real Time Operations
     