126583MARKET SYSTEMS17/04/2025 03:23:02 PM

CHG0102489 - Pre-Prod eMDM Maintenance Release

Change Number: CHG0102489

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Change Start Date & Time: 22/04/2025 13:00:00
Change End Date & Time: 22/04/2025 17:00:00
Outage Start Date & Time: 22/04/2025 13:00:00
Outage End Date & Time: 22/04/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126580POWER SYSTEM EVENTS17/04/2025 12:38:34 PM

Update - Non-credible contingency event - QLD region - 16/04/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 16/04/2025

Refer AEMO Electricity Market Notice 126579

At 1231 hrs the Greenbank - Molendinar 8825 275kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
126579POWER SYSTEM EVENTS16/04/2025 11:10:49 PM

Non-credible contingency event - QLD region - 16/04/2025

AEMO ELECTRICITY MARKET NOTICE.

Refer market notice: 126577

Non-credible contingency event - QLD region - 16/04/2025

At 2110 hrs the Greenbank - Molendinar 8825 275kV line tripped at the Molendinar end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
126560RESERVE NOTICE14/04/2025 06:13:59 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126559 is cancelled at 1811 hrs 14/04/2025.

Manager NEM Real Time Operations
     
126559RESERVE NOTICE14/04/2025 05:48:58 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/04/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1588 MW
The minimum capacity reserve available is 1553 MW

Manager NEM Real Time Operations
     
126545RESERVE NOTICE14/04/2025 05:18:07 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 14/04/2025 to 1800 hrs 14/04/2025.
The forecast capacity reserve requirement is 1537 MW.
The minimum capacity reserve available is 1365 MW.


Manager NEM Real Time Operations
     
126542RESERVE NOTICE14/04/2025 04:06:35 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126538 is cancelled at 1600 hrs 14/04/2025.

Manager NEM Real Time Operations
     
126538RESERVE NOTICE14/04/2025 01:52:48 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1700 hrs 14/04/2025 to 1830 hrs 14/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1141 MW.


Manager NEM Real Time Operations
     
126527RESERVE NOTICE13/04/2025 12:53:53 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 14/04/2025 to 1800 hrs 14/04/2025.
The forecast capacity reserve requirement is 1632 MW.
The minimum capacity reserve available is 1392 MW.


Manager NEM Real Time Operations
     