STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.
2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Refer to Market Notice 127682
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127792
Direction is cancelled from: 1400 hrs 25/06/2025
Manager NEM Real Time Operations
CHG0103089 - ERI & STPASA Recall Period Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025
Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127740
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/06/2025.
The direction update is issued at 1600 hrs 24/06/2025.
Manager NEM Real Time Operations
Completed - CHG0103783 - Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127753 is cancelled at 0900 hrs on 24/06/2025.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:
[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.
[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations