Cancellation - AEMO Intervention Event - SA region 22/05/2025
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Refer to Market Notice 127159
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127276
Direction is cancelled from: 1400 hrs 27/05/2025
Manager NEM Real Time Operations
Initial - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Change Start Date & Time: 28/05/2025 13:00:00
Change End Date & Time: 28/05/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: no outage, deployment will be made to msats 1a first then switch to msats 1b.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025
Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025
At 0337 hrs 27/05/2025 there was an unplanned outage of Brinkworth - Templers West 275 kV line.
The following constraint set(s) invoked at 0340 hrs 27/05/2025
S-BRTW
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127232
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 26/05/2025.
Manager NEM Real Time Operations
Completed - CHG0103179 - Scheduled maintenance of Marketnet router in Brisbane
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Woolooga No. 4 275 kV SVC - QLD region - 26/05/2025
Inter-regional transfer limit variation - Woolooga No. 4 275 kV SVC - QLD region - 26/05/2025
At 0808 hrs 26/05/2025 there was an unplanned outage of Woolooga No. 4 275 kV SVC.
The following constraint set(s) invoked at 0815 hrs 26/05/2025
Q-WO_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127193
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 25/05/2025.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127165
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/05/2025.
The direction update is issued at 1540 hrs 24/05/2025.
Manager NEM Real Time Operations