127647RESERVE NOTICE17/06/2025 02:24:32 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127637 is cancelled at 1410 hrs 17/06/2025.

Manager NEM Real Time Operations
     
127637RESERVE NOTICE17/06/2025 01:06:19 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 18/06/2025 to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 938 MW.
The minimum capacity reserve available is 812 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127626GENERAL NOTICE17/06/2025 01:30:24 PM

Planned outage of Moorabool - Cressy No 1 500 kV line in the VIC region on 19/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Moorabool - Cressy No 1 500 kV line in the Victoria (VIC) region is planned to be out of service from 0600 hrs to 1700 hrs on 19/06/2025.

A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM.

During this planned outage:

* Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
* Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
127625MARKET SYSTEMS17/06/2025 10:38:08 AM

Initial - CHG0103463 - EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities

Change Number: CHG0103463

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 19/06/2025 08:00:00
Change End Date & Time: 19/06/2025 22:00:00
Outage Start Date & Time: 19/06/2025 18:00:00
Outage End Date & Time: 19/06/2025 19:00:00
Environment: Production
Participant Impact and Requirements: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities. During the window, delivery of FPP calculations through the participant data model may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127624MARKET SYSTEMS17/06/2025 10:32:34 AM

Completed - CHG0103273 - Scheduled Maintenance on Brisbane Datacentre

Change Number: CHG0103273

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled Maintenance on Brisbane Datacentre

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127623RESERVE NOTICE17/06/2025 08:53:51 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 1047 MW.
The minimum capacity reserve available is 957 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127605RESERVE NOTICE16/06/2025 05:37:52 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127604 is cancelled at 1700 hrs 16/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127604RESERVE NOTICE16/06/2025 05:12:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0700 hrs to 0830 hrs 18/06/2025.
The forecast capacity reserve requirement is 1086 MW.
The minimum capacity reserve available is 896 MW.

2. From 1630 hrs to 1700 hrs 18/06/2025.
The forecast capacity reserve requirement is 1128 MW.
The minimum capacity reserve available is 922 MW.

3. From 1730 hrs to 1900 hrs 18/06/2025.
The forecast capacity reserve requirement is 1167 MW.
The minimum capacity reserve available is 1135 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127603MARKET INTERVENTION16/06/2025 03:04:43 PM

Cancellation - AEMO Intervention Event - SA region 15/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 15/06/2025

Refer to Market Notice 127557

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 16/06/2025.


Manager NEM Real Time Operations
     