Market Notices

127508NON-CONFORMANCE12/06/2025 12:10:21 AM

NON-CONFORMANCE Region VIC1 Thursday, 12 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 12 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 12/06/2025 00:05 to 12/06/2025 00:10
Amount: 14 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
127474GENERAL NOTICE08/06/2025 12:12:12 AM

Network Augmentation Commissioned - NSW Region - 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:

Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:

Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line

Manager NEM Real Time Operations
     
127404NON-CONFORMANCE05/06/2025 08:10:13 PM

NON-CONFORMANCE Region QLD1 Thursday, 5 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 5 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/06/2025 19:30 to 05/06/2025 20:10
Amount: 23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127365NON-CONFORMANCE03/06/2025 03:05:16 PM

NON-CONFORMANCE Region QLD1 Tuesday, 3 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 3 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 03/06/2025 15:00 to 03/06/2025 15:05
Amount: -33 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127360NON-CONFORMANCE02/06/2025 09:45:12 PM

NON-CONFORMANCE Region NSW1 Monday, 2 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 2 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 02/06/2025 21:40 to 02/06/2025 21:45
Amount: 9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127351NON-CONFORMANCE01/06/2025 11:55:15 PM

NON-CONFORMANCE Region QLD1 Sunday, 1 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 1 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#1
Duration: 01/06/2025 23:50 to 01/06/2025 23:55
Amount: -11 MW
Constraint: NC-Q_TARONG#1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127341NON-CONFORMANCE31/05/2025 12:50:15 PM

NON-CONFORMANCE Region QLD1 Saturday, 31 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 31 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/05/2025 12:30 to 31/05/2025 12:50
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127340NON-CONFORMANCE30/05/2025 11:00:14 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/05/2025 22:25 to 30/05/2025 23:00
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127337NON-CONFORMANCE30/05/2025 01:00:13 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/05/2025 11:50 to 30/05/2025 13:00
Amount: -63 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     