Market Notices

126487RESERVE NOTICE10/04/2025 05:44:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW

Manager NEM Real Time Operations
     
126486PRICES UNCHANGED10/04/2025 05:25:21 PM

[EventId:202504101700_confirmed] Prices for interval 10-Apr-2025 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:00.

In accordance with Market Notice 126474 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126485PRICES UNCHANGED10/04/2025 05:25:20 PM

[EventId:202504101725_confirmed] Prices for interval 10-Apr-2025 17:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:25.

In accordance with Market Notice 126480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126484PRICES UNCHANGED10/04/2025 05:25:20 PM

[EventId:202504101720_confirmed] Prices for interval 10-Apr-2025 17:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:20.

In accordance with Market Notice 126479 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126483PRICES UNCHANGED10/04/2025 05:25:20 PM

[EventId:202504101715_confirmed] Prices for interval 10-Apr-2025 17:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:15.

In accordance with Market Notice 126478 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126482PRICES UNCHANGED10/04/2025 05:25:20 PM

[EventId:202504101710_confirmed] Prices for interval 10-Apr-2025 17:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:10.

In accordance with Market Notice 126476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126481PRICES UNCHANGED10/04/2025 05:25:20 PM

[EventId:202504101705_confirmed] Prices for interval 10-Apr-2025 17:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025

PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:05.

In accordance with Market Notice 126475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126471MARKET INTERVENTION10/04/2025 03:21:04 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/04/2025

Refer Market Notice 126468

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1520 hrs 10/04/2025.

Manager NEM Real Time Operations
     
126468MARKET INTERVENTION10/04/2025 01:01:05 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 11/04/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm