127673MARKET INTERVENTION20/06/2025 02:37:38 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 127672

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 21/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 20/06/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
127672MARKET INTERVENTION20/06/2025 02:07:56 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 21/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127661RESERVE NOTICE18/06/2025 03:14:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127651 is cancelled at 1400 hrs 18/06/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
127651RESERVE NOTICE17/06/2025 03:17:59 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0600 hrs to 0800 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1420 MW.

2. From 1630 hrs to 2300 hrs 19/06/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1487 MW.

AEMO Operations
     
127650RESERVE NOTICE17/06/2025 02:24:42 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 127645 is cancelled at 1412 hrs 17/06/2025.

Manager NEM Real Time Operations
     
127649RESERVE NOTICE17/06/2025 02:24:42 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127638 is cancelled at 1412 hrs 17/06/2025.

Manager NEM Real Time Operations
     
127648RESERVE NOTICE17/06/2025 02:26:23 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127646 is cancelled at 1411 hrs 17/06/2025.

Manager NEM Real Time Operations
     
127647RESERVE NOTICE17/06/2025 02:24:32 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127637 is cancelled at 1410 hrs 17/06/2025.

Manager NEM Real Time Operations
     
127646RESERVE NOTICE17/06/2025 01:06:41 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 18/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1800 hrs 18/06/2025 to 1930 hrs 18/06/2025.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 508 MW.


Manager NEM Real Time Operations
     