Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - SA region 08/07/2025
Cancellation - AEMO Intervention Event - SA region 08/07/2025
Refer to Market Notice 128006
The AEMO Intervention Event and all associated directions are cancelled from 0730 hrs on 09/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128012
Direction is cancelled from: 0730 hrs 09/07/2025
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
Cancellation of Actual (LOR1) condition in the NSW region - 08/07/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.128020 is cancelled at 2000 hrs 08/07/2025.
Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127999 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1905 hrs 08/07/2025
Constraint set(s) revoked: I-VS_250
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/07/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1720 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 924 MW
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 09/07/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 128007
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0730 hrs 09/07/2025.
The direction update is issued at 1445 hrs 08/07/2025.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/07/2025
Cancellation - AEMO Intervention Event - SA region 06/07/2025
Refer to Market Notice 127966
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/07/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127995
Direction is cancelled from: 1500 hrs 08/07/2025
Manager NEM Real Time Operations