Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 07/06/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127413
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 07/06/2025.
The direction update is issued at 0915 hrs 07/06/2025.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_ML invoked from 0920 hrs.
The constraint set contains equations with the following interconnector on the LHS:
V-S-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Correction to Market Notice 127432
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1915 hrs 06/06/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1815 hrs 06/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1694 MW
The minimum capacity reserve available is 1692 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/06/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 06/06/2025 to 1800 hrs 06/06/2025.
The forecast capacity reserve requirement is 1598 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127412
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 06/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1900 hrs 06/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/06/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.